1.Use hose to install under the well :
The submersible electric pump which is installed under the well of the soft pipe can be directly used for hoisting the rope (such as nylon rope, etc.) which can bear the full weight of the water in the submersible electric pump and the water pipe and the water pipe and the water pipe and the water pipe.
2.The installation of steel pipe under the well :
The installation steps are as follows: the installation of the steel pipe under the well and using the submersible electric pump:
1).With the clamp top wells with submersible pump submersible pump parts, and the chain hoist, slowly, well, until the clamps secure resting on the wellhead, remove the chain.
2).Another pay clamp of a connecting pipe, flange connecting pipe distance 15cm with chain hoist, slowly down. Connecting pipe to the blue and submersible pump flange gasket between the good rubber gasket, bolts, nuts and spring washers will be connected to the pipe flange and submersible electric pump flange evenly forced tightening.
3).The submersible pump slightly lifted, remove the clamp at the upper end of the submersible pump, and use plastic tape or cable to connect cable card will fasten the hose, slowly under the hoop firmly resting on the wellhead.
4).With the same method, all the water pipes connected to the submersible pump, and human wells.
5).The submersible pump leads to the cable access control switch, and then connected three-phase power supply.