Installation and installation work order of submersible axial flow pump

 Anxial  flow pump

 

Preparation before installation :

1. Measuring and checking the installation position of the axial flow pump in the construction site and measuring the discharge line to determine the installation coordinate of axial flow pump and shaft axis reference line. 
2.  Inspection and acceptance, the quality inspection of the appearance of the axial flow pump and the shaft parts, and random data should be complete. 
 
3. Artificial crane, truck after unpacking inspection of axial flow pump, shaft parts and transport to the construction site. 

 